Abstract

The safety and stability of the cavern, as well as the settlement deformation of the sensitive buildings on the surface, are the problems of the shallow tunnel under the railway station, which is the key and difficult point in the control of the influence of the adjacent construction. It is quite important to choose a reasonable construction method. In view of the situation that the Kunming section of the Kunming-Chenggong tunnel of the Yunnan Central Water Diversion Project, which passes through the Jinmacun station, is faced with the situation of crossing the water-rich soft soil and the complex and sensitive surface environment, and the construction impact control requirements are extremely high. By means of field monitoring and numerical simulation, the three construction methods of the three-bench method, three-bench with temporary inverted arch method, and cross middle partition method are comprehensively compared and analyzed from the aspects of surrounding rock stability, surface settlement deformation, construction period, and investment. The results show that the settlement of railway subgrade by the three-bench method exceeds the control value. The cross middle partition method and the three-bench temporary inverted arch method both meet the requirements of cavern stability and surface deformation control, but the three-bench temporary inverted arch method is better in terms of construction period and economy, which is the final recommended method. The current monitoring data and tunnel excavation support practice show that the tunnel is generally safe and stable, and the surface settlement deformation is controllable, which can provide experience for similar projects.

Cite this article

Li Wu , Xiang Tianbing , Yang Xiaolong , Yan Shanglong , Fu Mengdie . Comparison and Selection Study on Construction Methods for Shallow Buried Tunnel Underpassing Railway Station[J]. Chinese Journal of Underground Space and Engineering, 2026 , 22(S1) : 294 -300 . DOI: 10.20174/j.JUSE.2026.S1.32

References

[1] 黄辉, 吴晔晖, 谢文达, 等. 淤泥地层盾构下穿密集房屋沉降控制技术研究[J]. 土木工程学报, 2024, 57(增1):154-162.
[2] 谢雄耀, 张永来, 周彪, 等. 盾构隧道下穿老旧建筑物群微沉降控制技术研究[J]. 岩土工程学报, 2019, 41(10):1781-1789.
[3] 方广涛, 方华昌, 涂怀宇, 等. 砂卵石地层盾构下穿高速公路加固方案研究[J]. 地下空间与工程学报, 2022, 18(增2):841-849.
[4] 赵亮亮, 杨文波, 潘文韬, 等. 不同大变形等级的层状软岩隧道施工模型试验与数值模拟研究[J]. 岩石力学与工程学报, 2024, 43(2):454-467.
[5] 樊纯坛, 梁庆国, 房志群, 等. 施工方法对黄土隧道围岩结构相互作用的影响[J]. 铁道工程学报, 2022, 39(11):81-87.
[6] 刘天琦, 冯现大, 何家智. 公路隧道改扩建方案比选及施工工法数值模拟[J]. 济南大学学报(自然科学版), 2025, 39(1):56-62.
[7] 姜封国, 白丽丽, 宋敏, 等. 哈尔滨城市地铁大断面隧道施工稳定性分析[J]. 吉林大学学报(工学版), 2020, 50(4):1419-1427.
[8] 杨子璇, 姚爱军, 张东, 等. 隧道密贴下穿既有地铁车站沉降控制研究[J]. 地下空间与工程学报, 2020, 16(增1):442-449, 464.
[9] 张丙强, 刘海, 罗才松. 新建隧道下穿施工引起既有铁路轨道变形的理论计算模型[J]. 铁道学报, 2023, 45(10):105-111.
[10] 王圣涛, 冯冀蒙. 黏质黄土地层高铁隧道变形控制基准研究[J]. 地下空间与工程学报, 2022, 18(3):973-981.
[11] 国家铁路局. 邻近铁路营业线施工安全监测技术规程(TB 10314—2021)[S]. 北京:中国铁道出版社,2021.
Outlines

/

〈 〉