Excavation Methods for Super-Large Span Dome-Vertical Wall Underground Tanks

  • Bai Dongfeng ,
  • Yao Hongzhi ,
  • Shi Baotong ,
  • Guo Tengfei ,
  • Cheng Yuanhu
Expand
  • CCCC First Highway Consultants Co., Ltd., Xi'an 710075, P. R. China

Received date: 2025-10-15

  Online published: 2026-09-29

摘要

为了研究超大跨穹顶直墙地下罐体的合理开挖方法,以某Ⅳ级围岩超大跨罐体为研究对象,提出了三种开挖方法:环形开挖法、条形开挖法及走“8”字开挖法。通过数值模拟研究了三种开挖方法下罐体的力学响应规律,并综合考虑施工效率、工期、造价等因素,优选出不同围岩情况下的合理工法。结果表明:(1)环形开挖法在外环/内环开挖阶段围岩变形平缓,但在中岩柱解除时易引发变形阶跃现象;(2)条形开挖法变形发展相对平缓,且施工后期变形发展较前期缓慢;(3)走“8”字开挖法前中期变形稳定性最佳,施工后期的变形介于另两种工法之间;(4)三种施工开挖方法在施工效率上排序为环形开挖法>条形开挖法>走“8”字开挖法,而在受力性能方面,走“8”字开挖法因应力分布均匀性最佳,结构变形控制效果最优;(5)综合考虑施工安全性、工程造价和施工效率,对于地质条件良好的区域,环形开挖法断面标准化、工效高、造价低,可作为优选工法,对于围岩破碎容易失稳的区域推荐采用条形开挖法或走“8”字开挖法。研究成果可为不同地质条件下超大跨罐体施工开挖方法选择提供理论依据。

本文引用格式

白东锋 , 姚红志 , 史宝童 , 郭腾飞 , 程元虎 . 超大跨穹顶直墙地下罐体开挖方法研究[J]. 地下空间与工程学报, 2026 , 22(S1) : 312 -320 . DOI: 10.20174/j.JUSE.2026.S1.34

Abstract

To study the rational excavation methods for super-large-span underground storage tanks with dome roofs and vertical walls, this study takes a super-large-span tank in Class IV surrounding rock as the research object. Three excavation methods are proposed:the annular excavation method, the strip excavation method, and the figure-eight excavation method. Numerical simulations were employed to study the mechanical response laws of the tank under these three excavation methods. By comprehensively considering factors such as construction efficiency, schedule, and cost, the optimal method for different surrounding rock conditions was prioritized. The research results indicate that:(1) The annular excavation method exhibits gradual surrounding rock deformation during the outer/inner ring excavation stages, but is prone to triggering a sudden deformation jump upon the removal of intermediate rock pillars. (2) The strip excavation method shows relatively stable deformation development, with slower progression in later construction stages compared to earlier stages. (3) The figure-eight excavation method demonstrates optimal deformation stability during initial and intermediate stages, with its late-stage performance falling between the other two methods. (4) Regarding construction efficiency, the methods rank as follows:annular excavation > strip excavation > figure-eight excavation. In terms of mechanical performance, the figure-eight excavation method achieves the most uniform stress distribution and delivers superior structural deformation control. (5) Considering construction safety, project cost, and efficiency:For areas with favorable geological conditions, the annular excavation method—featuring standardized cross-sections, high efficiency, and low cost—is recommended as the preferred method. For areas with fractured surrounding rock prone to instability, either the strip excavation method or the figure-eight excavation method is advised. The research outcomes provide a theoretical basis for selecting excavation methods for super-large-span storage tanks under diverse geological conditions.

参考文献

[1] 吴俊杰.阿尔塔什水利枢纽埋藏式调压井穹顶施工数值仿真[J].中国水利水电科学研究院学报,2020,18(5):388-394.
[2] 张治军,苏利军,李锋.地下核反应堆洞室大型穹顶施工三维模拟研究[J].人民长江,2016,47(3):59-62.
[3] 张乃嘉,陶连金,安韶,等.不同地应力特征下超大跨扁平地下洞室水平地震响应分析[J].科学技术与工程,2022,22(9):3716-3721.
[4] 乔春生,王可,贺维国,等.超大跨扁平地下洞室围岩分级方法探讨[J].隧道建设(中英文),2023,43(9):1443-1454.
[5] 陶连金,黄琳昆,石城,等.超大跨度扁平地下洞室变形控制标准研究[J].隧道建设(中英文),2022,42(1):9-15.
[6] 苏利军,刘立新,李锋,等.地下核电厂大型洞室群开挖施工关键技术研究[J].核动力工程,2016,37(5):156-160.
[7] 孟国涛,吕慷,陈益民,等.高应力条件下巨型地下洞室穹顶施工方案比较[J].科技通报,2017,33(1):205-211.
[8] 马凯蒙,张俊儒,刘雨萌,等.基于现场试验的超大双曲面穹顶洞库支护体系研究[J].隧道建设(中英文),2022,42(7):1257-1266.
[9] 王帅帅,郭亚斌,王星,等.超大跨地下洞室开挖支护方案与工程应用研究[J].现代隧道技术,2022,59(增1):993-1003.
[10] 徐干成,袁伟泽,徐景茂,等.大跨度扁平地下洞室开挖方案研究[J].地下空间与工程学报,2018,14(增2):763-768, 773.
[11] 张春生,刘宁,陈建林,等.“2S+”大型地下洞室支护设计方法与应用[J].岩石力学与工程学报,2023,42(1):51-64.
[12] 孙会想,汪海平.特大型圆筒式尾水调压室穹顶施工通风技术[J].地下空间与工程学报,2019,15(5):1519-1527.
文章导航

/

〈 〉