设计、施工、监测

小净距大断面城市隧道不中断交通扩挖支护方法研究

  • 雷明锋 ,
  • 扎西草 ,
  • 杜三虎 ,
  • 王立川 ,
  • 郑穇然
展开
  • 1.中南大学 土木工程学院,长沙 410075;
    2.中铁十八局集团有限公司,天津 300350;
    3.中铁十八局集团市政工程有限公司,天津 300350;
    4.山东大学 齐鲁交通学院,济南 250357;
    5.福州市市政建设开发有限公司,福州 350000
雷明锋(1982—),男,湖南祁东人,博士,教授,主要从事隧道与下工程方面的教学与科研工作。E-mail:mingdfenglei@csu.edu.cn
扎西草(2002—),女,甘肃甘南藏族自治州人,博士生,主要从事隧道及地下工程方面研究。E-mail:244807005@csu.edu.cn

收稿日期: 2025-10-06

  网络出版日期: 2026-09-29

基金资助

中铁十八局集团有限公司科技研发计划项目(CR18GK-24-S-P-10)

Research on Support Methods for Non-Traffic-Interruption Expansion of Small-Spacing Large-Section Urban Tunnels

  • Lei Mingfeng ,
  • Zha Xicao ,
  • Du Sanhu ,
  • Wang Lichuan ,
  • Zheng Canran
Expand
  • 1. School of Civil Engineering, Central South University, Changsha 410075, P. R. China;
    2. China Railway 18th Bureau Group Co., Ltd., Tianjin 300350, P. R. China;
    3. Municipal Engineering Co., Ltd., China Railway 18th Bureau Group, Tianjin 300350, P. R. China;
    4. School of Qilu Transportation, Shandong University, Jinan 250357, P. R. China;
    5. Fuzhou Municipal Construction and Development Co., Ltd., Fuzhou 350000, P. R. China

Received date: 2025-10-06

  Online published: 2026-09-29

摘要

为研究城市浅埋隧道大断面扩建对对既有运营隧道的影响,并对扩建全过程安全性进行评价,以福州市象山隧道改扩建工程为工程背景,针对大断面浅埋隧道建立考虑隔离桩、抗浮桩、锚杆小导管及初期支护二衬的扩建全过程三维精细化数值模型,通过与隧道扩建施工监测资料进行对比,验证了数值模型的可靠性。结果表明:(1)上层隧道的开挖扩建为引起地表沉降及隧道周边扩建的控制工序,新旧隧道交界处附近初期支护拉应力较大;(2)对隧道扩建全过程进行安全性评估,发现当前支护措施及开挖步序下工程安全性总体可控,锚杆轴力(+39.74%)为主要风险源;(3)采用现有的支护措施扩建过程对既有运营隧道的影响较小,无需对其进行额外加固。

本文引用格式

雷明锋 , 扎西草 , 杜三虎 , 王立川 , 郑穇然 . 小净距大断面城市隧道不中断交通扩挖支护方法研究[J]. 地下空间与工程学报, 2026 , 22(S1) : 301 -311 . DOI: 10.20174/j.JUSE.2026.S1.33

Abstract

To investigate the impact of large-section urban shallow-buried tunnel expansion on existing operational tunnels and evaluate the safety throughout the expansion process, this study takes the expansion project of Fuzhou Xiangshan Tunnel as a case study. A detailed three-dimensional numerical model simulating the entire expansion process was established, incorporating isolation piles, anti-floating piles, rock bolts, forepoling pipes, and primary and secondary linings. Comparison with field monitoring data from the tunnel expansion construction demonstrated a high degree of consistency with the numerical simulation results, verifying the reliability of the numerical model. The results indicate that:(1) The excavation of the upper tunnel is the controlling process for inducing surface settlement and deformation around the tunnel periphery, with significant tensile stresses occurring in the primary support near the interface between the new and existing tunnels. (2) Safety assessment throughout the tunnel expansion process reveals that the project safety is generally manageable under the current support measures and excavation sequence, with the axial force of rock bolts (+39.74%) identified as the primary risk source. (3) The expansion process, utilizing the existing support measures, has a minor impact on the existing operational tunnel, eliminating the need for additional reinforcement.

参考文献

[1] 李秀地, 蒋树屏, 刘元雪, 等. 小净距新建隧道爆破对运营隧道的影响与控制[J]. 地下空间与工程学报, 2016, 12(6):1631-1636.
[2] 谭仪忠, 刘元雪, 周家伍, 等. 隧道单侧扩建跳槽式开挖方法合理槽宽的确定[J]. 地下空间与工程学报, 2013, 9(1):147-154.
[3] 梁晓林, 伍圣华, 曾祥泽, 等. 矿山法隧道改扩建围岩及支护结构稳定性研究[J]. 科技通报, 2024, 40(12):76-83.
[4] 张众. 不间断运营既有交通隧道改扩建关键技术综述及工程应用[J]. 特种结构, 2025, 42(2):38-44.
[5] 赖勇, 张帅. 流固耦合作用下浅埋偏压隧道扩建方式研究[J]. 隧道建设(中英文), 2019, 39(增2):17-27.
[6] 张雷, 王飞. 连拱隧道改扩建方案探讨与研究[J]. 隧道建设(中英文), 2019, 39(增1):346-354.
[7] 谭仪忠, 刘元雪, 蔡守军, 等. 浅埋隧道单侧扩建施工方案优化[J]. 公路交通科技, 2019, 36(4):108-116.
[8] 刘天琦. 既有公路隧道原位扩建施工力学特性及支护参数研究[D]. 济南:济南大学, 2024.
[9] 吴佳顺, 朱云升, 张文权. 高液限红粘土高填方路堤稳定性及变形特性研究[J]. 公路交通科技(应用技术版), 2020, 16(5):6-11.
[10] 张民. 高填方土工格栅加筋路堤稳定性分析[J]. 天津建设科技, 2020, 30(5):12-14.
[11] 陈涛, 杨万全. 山区斜坡软弱地基上高填方路堤变形及稳定性分析[J]. 市政技术, 2019, 37(3):45-48.
[12] 林从谋,张在晨,郑强等.小净距隧道原位二扩四CD工法软弱围岩稳定性及支护参数研究[J].土木工程学报,2013,46(7):124-132.
[13] Vetter S, Galli M, Steiner P. Refurbishment of the kuckuckslay tunnel-current experience in the use of the ″tunnel-im-tunnel-methode″[J]. Geomechanics and Tunnelling, 2020, 13(5):557-565.
[14] 彭念. 原位扩建隧道围岩力学响应机理研究[D]. 重庆:重庆大学, 2011.
[15] 柏谦, 赵文, 王鑫, 等. 既有改扩建浅埋岩石隧道的围岩压力计算方法研究[J]. 中南大学学报(自然科学版), 2021, 52(5):1562-1569.
[16] 来弘鹏, 徐学深, 常瑞成, 等. 公路隧道扩建力学特征研究[J]. 中国公路学报, 2014, 27(1):84-93.
[17] 刘学. 分离式隧道扩建成小净距隧道群模型试验研究[J]. 公路交通科技(应用技术版), 2018, 14(3):152-155.
[18] 贾艳领, 周绍文, 王刚, 等. 既有隧道扩建为双连拱隧道中隔墙受力特征研究[J]. 现代隧道技术, 2021, 58(3):130-138.
[19] 刘泉声, 孙兴山, 苏兴矩, 等. 后祠改(扩)建隧道施工方案优化分析[J]. 武汉大学学报(工学版), 2016, 49(4):544-551.
[20] 朱育才, 林志, 石波. 隧道扩建对地面建筑物的影响分析[J]. 重庆交通大学学报(自然科学版), 2011, 30(5):938-942.
文章导航

/

〈 〉