设计、施工、监测

浅埋隧洞下穿铁路站场施工工法比选研究

  • 李武 ,
  • 向天兵 ,
  • 杨小龙 ,
  • 闫尚龙 ,
  • 付梦蝶
展开
  • 1.昆明理工大学 公共安全与应急管理学院,昆明 650093;
    2.中国电建集团昆明勘测设计研究院有限公司,昆明 650051
李武(2001—),男,湖南益阳人,硕士生,主要从事安全工程与岩土工程方面的研究。E-mail:1985560309@qq.com
向天兵(1983—),男,河南南阳人,硕士,正高级工程师,主要从事岩土工程、地下工程等领域的设计和科研工作。E-mail:xiangtb_kmy@powerchina.cn

收稿日期: 2026-04-14

  网络出版日期: 2026-09-29

基金资助

云南省技术创新中心建设项目(202305AK340003);电建集团重点科技项目(DJ-ZDXM-2024-29);电建昆明院重点科技项目(KD-ZDYF2003-004)

Comparison and Selection Study on Construction Methods for Shallow Buried Tunnel Underpassing Railway Station

  • Li Wu ,
  • Xiang Tianbing ,
  • Yang Xiaolong ,
  • Yan Shanglong ,
  • Fu Mengdie
Expand
  • 1. Faculty of Public Security and Emergency Management, Kunming University of Science and Technology, Kunming 650093, P. R. China;
    2. PowerChina Kunming Engineering Corporation Limited, Kunming 650051, P. R. China

Received date: 2026-04-14

  Online published: 2026-09-29

摘要

浅埋隧洞下穿铁路站场存在洞室安全稳定和地表敏感建筑物沉降变形控制的问题,选择合理的施工工法至关重要。针对滇中引水工程昆明段昆呈隧洞下穿金马村车站段面临穿越富水软弱土体、地表环境复杂敏感的情况,采用现场监测和数值模拟的方法,从围岩稳定性、地表沉降变形以及工期投资等方面对三台阶法、三台阶临时仰拱法和交叉中隔壁法三种施工工法进行了综合比选分析。结果表明:三台阶法铁路路基沉降超出控制值,交叉中隔壁法和三台阶临时仰拱法对洞室稳定和地表变形控制均满足要求,三台阶临时仰拱法在工期和经济性方面更优。当前监测数据和隧洞开挖支护实践表明,隧洞总体安全稳定,地表沉降变形可控,可为类似工程提供经验借鉴。

本文引用格式

李武 , 向天兵 , 杨小龙 , 闫尚龙 , 付梦蝶 . 浅埋隧洞下穿铁路站场施工工法比选研究[J]. 地下空间与工程学报, 2026 , 22(S1) : 294 -300 . DOI: 10.20174/j.JUSE.2026.S1.32

Abstract

The safety and stability of the cavern, as well as the settlement deformation of the sensitive buildings on the surface, are the problems of the shallow tunnel under the railway station, which is the key and difficult point in the control of the influence of the adjacent construction. It is quite important to choose a reasonable construction method. In view of the situation that the Kunming section of the Kunming-Chenggong tunnel of the Yunnan Central Water Diversion Project, which passes through the Jinmacun station, is faced with the situation of crossing the water-rich soft soil and the complex and sensitive surface environment, and the construction impact control requirements are extremely high. By means of field monitoring and numerical simulation, the three construction methods of the three-bench method, three-bench with temporary inverted arch method, and cross middle partition method are comprehensively compared and analyzed from the aspects of surrounding rock stability, surface settlement deformation, construction period, and investment. The results show that the settlement of railway subgrade by the three-bench method exceeds the control value. The cross middle partition method and the three-bench temporary inverted arch method both meet the requirements of cavern stability and surface deformation control, but the three-bench temporary inverted arch method is better in terms of construction period and economy, which is the final recommended method. The current monitoring data and tunnel excavation support practice show that the tunnel is generally safe and stable, and the surface settlement deformation is controllable, which can provide experience for similar projects.

参考文献

[1] 黄辉, 吴晔晖, 谢文达, 等. 淤泥地层盾构下穿密集房屋沉降控制技术研究[J]. 土木工程学报, 2024, 57(增1):154-162.
[2] 谢雄耀, 张永来, 周彪, 等. 盾构隧道下穿老旧建筑物群微沉降控制技术研究[J]. 岩土工程学报, 2019, 41(10):1781-1789.
[3] 方广涛, 方华昌, 涂怀宇, 等. 砂卵石地层盾构下穿高速公路加固方案研究[J]. 地下空间与工程学报, 2022, 18(增2):841-849.
[4] 赵亮亮, 杨文波, 潘文韬, 等. 不同大变形等级的层状软岩隧道施工模型试验与数值模拟研究[J]. 岩石力学与工程学报, 2024, 43(2):454-467.
[5] 樊纯坛, 梁庆国, 房志群, 等. 施工方法对黄土隧道围岩结构相互作用的影响[J]. 铁道工程学报, 2022, 39(11):81-87.
[6] 刘天琦, 冯现大, 何家智. 公路隧道改扩建方案比选及施工工法数值模拟[J]. 济南大学学报(自然科学版), 2025, 39(1):56-62.
[7] 姜封国, 白丽丽, 宋敏, 等. 哈尔滨城市地铁大断面隧道施工稳定性分析[J]. 吉林大学学报(工学版), 2020, 50(4):1419-1427.
[8] 杨子璇, 姚爱军, 张东, 等. 隧道密贴下穿既有地铁车站沉降控制研究[J]. 地下空间与工程学报, 2020, 16(增1):442-449, 464.
[9] 张丙强, 刘海, 罗才松. 新建隧道下穿施工引起既有铁路轨道变形的理论计算模型[J]. 铁道学报, 2023, 45(10):105-111.
[10] 王圣涛, 冯冀蒙. 黏质黄土地层高铁隧道变形控制基准研究[J]. 地下空间与工程学报, 2022, 18(3):973-981.
[11] 国家铁路局. 邻近铁路营业线施工安全监测技术规程(TB 10314—2021)[S]. 北京:中国铁道出版社,2021.
文章导航

/

〈 〉