盐渍土路基含盐量的演化规律研究

  • 李飞 ,
  • 于振涛
展开
  • 中铁二院工程集团有限责任公司, 成都 610031
李飞(1981—),男,四川广元人,高级工程师,主要从事岩土工程领域的勘察设计工作。E-mail:375962020@qq.com

收稿日期: 2023-11-26

  网络出版日期: 2024-09-30

Study on the Evolution Law of Salt Content in Saline Soil Subgrade

  • Li Fei ,
  • Yu Zhentao
Expand
  • China Railway Eryuan Engineering Group Co. Ltd, Chengdu 610031, P. R. China

Received date: 2023-11-26

  Online published: 2024-09-30

摘要

虽然目前针对盐渍土的研究比较多,但基本上都集中在项目勘察设计及建设期,对利用盐渍土填筑的路堤中含盐量随时间变化的规律,国内外研究还比较少。为了探究盐渍土路基填料中含盐量随时间的变化规律,为改建项目中盐渍土路基设计提供理论支撑,本文依托巴基斯坦罗赫里至木尔坦段既有铁路提速改造项目,通过现场调查及大量现场试验,对比分析既有路基填料及两侧原状土中含盐量,总结出盐渍土路基变化规律。结果表明:采用盐渍土填筑的路堤,路基填土中含盐量随着时间推移逐渐降低,逐渐过渡为非盐渍土;对于新建路基采用盐渍土填筑时,采用加宽路基面、放缓路堤坡率等工程措施,同时优先安排施工,静置浸润后,可有效降低路基填料中含盐量,直接采用盐渍土填筑路基既节约工程投资,又能确保路基的安全稳定。

本文引用格式

李飞 , 于振涛 . 盐渍土路基含盐量的演化规律研究[J]. 地下空间与工程学报, 2024 , 20(S1) : 344 -349 . DOI: 10.20174/j.JUSE.2024.S1.41

Abstract

Although there is currently a lot of research on saline soil, it is mainly focused on project survey, design, and construction period. There is still relatively little research on the variation of salt content over time in embankments filled with saline soil at home and abroad. In order to explore the variation of salt content in saline soil roadbed fillers over time and provide theoretical support for the design of saline soil roadbed in the renovation project, this article relies on the existing railway speed-up renovation project from Rohri to Multan in Pakistan. Through on-site investigation and a large number of on-site tests, the salt content in the existing roadbed fillers and the undisturbed soil on both sides is compared and analyzed, and the variation law of saline soil roadbed is summarized. For embankments filled with saline soil, the salt content in the roadbed filling gradually decreases over time and transitions to non saline soil. When using saline soil to fill the newly built roadbed, engineering measures such as widening the roadbed surface and slowing down the slope rate of the embankment should be taken. At the same time, priority should be given to construction. After soaking, the salt content in the roadbed filling can be effectively reduced. Directly using saline soil to fill the roadbed not only saves engineering investment but also ensures the safety and stability of the roadbed.

参考文献

[1] 张永康,张田,张荣飞,等.高盐渍土地区某铁路路基填料选择研究[J].铁道工程学报,2016(9):9-13.
[2] 吴沛沛,陈伟志,丁兆峰.高烈度区盐湖软弱盐渍土地基加固关键技术[J].高速铁路技术,2018(2):37-42.
[3] 陈文化.重载铁路盐渍土路基中土工布使用寿命评估[J].铁道工程学报,2015(9):55-59.
[4] 吴亚平,梁浩,魏明强,等. 级配对粗颗粒硫酸盐渍土溶陷特性的影响[J].铁道工程学报,2019(1):12-16.
[5] 国家铁路局.铁路工程特殊岩土勘察规程(TB10038-2023)[S].北京:中国铁道出版社,2023.
[6] 中华人民共和国铁道部.铁路工程土工试验规程(TB 10102-2010)[S]. 北京:中国铁道出版社,2011.
[7] 国家铁路局.铁路特殊路基设计规范(TB 10035-2018)[S]. 北京:中国铁道出版社,2018.
[8] 张卫兵,李晓,雷过, 等. 冻融-干湿循环下硫酸盐渍土的微观孔隙研究[J]. 地下空间与工程学报,2023,19(2):465-473.
[9] 王静,魏艳蕾,宋泽凡. 松嫩平原盐渍土无侧限抗压强度研究[J]. 地下空间与工程学报,2010,6(6):1146-1151.
[10] 杨保存,刘新荣,贺兴宏,等. 盐渍土路基盐胀性试验研究[J]. 地下空间与工程学报,2009,5(3):594-603.
[11] 张卫兵,任亚军,周瑞璞. 单次升温条件下硫酸盐渍土的融沉试验研究[J]. 地下空间与工程学报,2022,18(3):868-874,882.
文章导航

/